New Campus Plan


History

1991 October Determination of relocation to Motooka/Kuwabara district, Nishi-ku, Fukuoka City
1993 August Establishment of New Campus Planning Office
November Determination of New Campus site
  • Fukuoka City 243 ha, Maebaru City 1 ha, Shima-machi 31 ha, total 275 ha
  • About 170 ha for building area; about 100 ha for preserved green area
1998 May Publication of “Basic Plan for New Campus Land Development”.
December Completion of land acquisition of New Campus site by Fukuoka City Land Development Corporation
1999 April Revision of “Basic Plan for New Campus Land Development”
July Determination of zoning and relocation sequence.
November Construction consultants for New Campus Master Plan decided.
  • MCM Design Group (Mitsubishi Jisho Sekkei, Cesar Pelli & Associates Japan, Mishima Architects)
2000 February Publication of “Environmental impact assessment on integrated relocation to Kyushu University's New Campus”.
Determination of concept on New Campus Master Plan.
March Determination of Basic Design for New Campus Development.
June Start of land formation work of Sector I
2001 March Determination of New Campus Master Plan 2001.
2002 March Completion of Land formation work of Sector I (engineering-related zone, 50.5 ha).
April Determination of New Campus operation schedule (October 2005).
June Determination of basic design for Engineering-Related Zone.
2003 January Start construction of Engineering-Related Research and Education Building II and III .
  • About 2,000 students and faculty members in mechanical and aeronautical engineering and materials science.
  • Floor area: about 45,000 m2
  • Completion scheduled for May 2005 and relocation for October 2005.
February Start of land formation work of Sector III.
June Determination of basic design for Center Zone
2004 April Start construction of Engineering-Related Research and Education Building I.
  • About 2,300 students and faculty members in global environment and system information.
  • Floor area: 50,400 m2
  • Completion scheduled for May 2006 and relocation for FY 2006.
September Publication of “Public Space Design Manual”
2005 February Start of land formation work of Sector II.
April Determination of New Campus name as “Ito Campus”.
October Start of operation on Ito Campus